Cut, fill and net earthwork by the grid method — the one a site engineer uses, not area times average depth.

Cut & Fill
Start from

Distance between grid lines. The site is 2 × 2 cells, so it spans twice this each way.

Net earthwork

Net earthwork: 0 cubic yards. The site balances — but look at the total moved.

cubic yards

The site balances — but look at the total moved.

Cut and fill, plan view
25 ft grid
0000cut (+)fill (−)
Cut
0cu ydIn-place volume removed.
Fill
0cu ydIn-place volume placed.
Total moved
0cu ydCut plus fill — what is actually handled, regardless of the net.
Material balance
cu ydAdd swell and shrink to see whether cut material covers the fill once bulked and compacted.

The working

  1. Cell area = Spacing²

    = 25 ft²

    = 625 ft²

  2. Cell volume = (average of 4 corner depths) × Cell area

    = 0 ft, 0 ft, 0 ft, 0 ft × area

    = 0 cu yd, 0 cu yd, 0 cu yd, 0 cu yd

    Positive cells are cut, negative cells are fill. Each is summed separately.

  3. Total cut = Σ positive cells

    = 0 cu yd

  4. Total fill = Σ |negative cells|

    = 0 cu yd

  5. Net = Cut − Fill

    = 0 cu yd − 0 cu yd

    = 0 cu yd

    Balanced.

Lay a grid over the site and, at each intersection, enter how far the existing ground sits above or below the proposed grade. The calculator works each cell separately, sums cut and fill on their own, and reports the net — while making sure the total moved is never hidden behind it.

How this calculator works

Specification
Formula version
1.0.0
Last reviewed
2026-09-01
External data
None

This tool uses only your inputs and exact unit conversions. No benchmark, average or market figure is built into it. How we calculate

What this calculates

Three volumes that are routinely confused. Cut is material removed where the ground is high. Fill is material placed where it is low. Net is the difference, and it decides whether material leaves the site or arrives. A fourth figure — total moved, cut plus fill — is what actually gets priced, and it is the one most tools hide.

The grid method

A square grid is laid over the site. At each intersection, the difference between existing and proposed elevation is recorded: positive where the ground must come down (cut), negative where it must come up (fill).

Each cell of the grid takes the average of its four corner depths and multiplies by the cell area. Cells with a positive average add to cut; negative, to fill. The two sums are kept separate the whole way through, because a site that nets to zero can still involve moving every yard on it.

Why not area times average depth

Averaging all the depths across a site and multiplying by the area gives you the net directly — and nothing else. It cannot tell you the cut or the fill, and on a site where they are both large and roughly equal it reports a small number for what is, in truck terms, a large job.

The grid method is what estimating software does with hundreds of points. This tool does it with nine, which is enough to be correct and few enough to follow.

Swell and shrink

Cut material bulks up once dug; fill material compacts once placed. Whether the cut covers the fill therefore depends on both factors, and both depend on the soil. They are optional inputs here and no default is assumed. With them entered, the calculator reports the loose surplus or shortfall; without them, it reports the in-place volumes and says what is missing.

Worked example

A sloping pad on a 25 ft grid: 2 ft of cut on the high side, 1 ft of fill on the low side

Given
Grid spacing
25 ft (cell area 625 sq ft)
North row
+2, +2, +2 ft
Middle row
+0.5, +0.5, +0.5 ft
South row
−1, −1, −1 ft
Step by step
  1. North cells (each)= (2 + 2 + 0.5 + 0.5) ÷ 4 × 625= 781 cu ft = 28.9 cu yd cut
  2. South cells (each)= (0.5 + 0.5 − 1 − 1) ÷ 4 × 625= −156 cu ft = 5.8 cu yd fill
  3. Total cut= 2 × 28.9= 57.9 cu yd
  4. Total fill= 2 × 5.8= 11.6 cu yd
  5. Net= 57.9 − 11.6= 46.3 cu yd export
Net46.3 cu yd to export, 69.4 cu yd moved
What it assumes
  • A regular 2 × 2-cell grid with uniform spacing — nine spot depths.
  • Ground and proposed surfaces vary linearly between grid points.
  • Depths are existing minus proposed, so cut is positive and fill is negative.
  • Swell and shrink apply only when entered.
What it does not do
  • Nine points is a teaching grid. A real site uses many more, and the same arithmetic — this tool shows the method, not a survey.
  • It does not handle a grid cell that is part cut and part fill within itself; the corner average decides the cell. Finer grids reduce this error.
  • It does not model topsoil strip, subgrade preparation or over-excavation.
  • It does not assume swell or shrink factors.

Common questions

What is the difference between net and total moved?
Net is cut minus fill — what leaves or arrives. Total moved is cut plus fill — what gets handled. A balanced site has a net of zero and can still have a very large total moved. Contractors price the second number.
Does the cut material cover the fill?
Not one-for-one. Cut bulks up when dug and fill compacts when placed, so the answer depends on both factors for your soil. Enter your swell and shrink and the calculator reports the loose surplus or shortfall.
Why only nine points?
Because that is enough to make the grid method real and few enough to follow by hand. A survey uses hundreds and the same arithmetic. If you have the data, split the site into 2 × 2 blocks and run each.

Found a problem?